- Major infrastructure win: AESL secures the project through the Tariff Based Competitive Bidding (TBCB) mechanism to evacuate power from Adani Power’s upcoming 2,400 MW Pirpainti Ultra Super Critical Thermal Power Plant.
- ₹500-crore annual revenue: The project is expected to generate an annual tariff of approximately ₹500 crore once commissioned.
- Expansive network addition: The project will add 881 circuit kilometres (ckm) of transmission lines and 3,160 MVA of transformation capacity to AESL’s growing portfolio.
- 2028 delivery target: The transmission infrastructure, including four Gas Insulated Substations (GIS), is scheduled for completion by the last quarter of 2028.
NE ENERGY BUREAU
AHMEDABAD, NOV 20
The journey of 2,400 MW of electricity from a power plant to homes, industries and businesses in Bihar is set to receive a major infrastructure boost, with Adani Energy Solutions Limited (AESL) securing a ₹500-crore annual-tariff transmission project that will strengthen the state’s power evacuation capabilities and expand its electricity network.
AESL, one of India’s leading private-sector power transmission and distribution companies, announced on Thursday that it had won the project through the Tariff Based Competitive Bidding (TBCB) mechanism. The scheme will facilitate the evacuation of power from Adani Power’s upcoming 2,400 MW (3X800 MW) Ultra Super Critical Thermal Power Plant at Pirpainti in Bihar.
Titled ‘Evacuation of Power from 3X800 MW STPP Pirpainti’, the project will be implemented through a Special Purpose Vehicle (SPV), Vikramshila Power Transmission Ltd., and is targeted for completion by the last quarter of 2028. Besides transmitting electricity generated at the upcoming plant, the infrastructure is expected to reinforce Bihar’s transmission backbone, improve grid reliability and enhance the state’s capacity to meet its growing electricity demand.
“The Pirpainti transmission scheme will create a robust evacuation system for 2,400 MW of generation capacity while strengthening Bihar’s transmission backbone. It will enhance grid reliability and resilience and help the state meet its growing power demand. We remain committed to building reliable and efficient transmission infrastructure that supports the country’s long-term energy security,” said Kandarp Patel, CEO, Adani Energy Solutions.
The project will add 881 circuit kilometres of transmission lines and 3,160 MVA of transformation capacity to AESL’s portfolio. Following its commissioning, the company’s transmission network will expand to 30,683 ckm, while its transformation capacity will rise to 146,585 MVA.
With this latest project win, AESL’s transmission capital expenditure portfolio stands at approximately ₹91,500 crore, underlining the scale of its ongoing investments in India’s electricity transmission infrastructure.
The project entails the construction of four Gas Insulated Substations (GIS) at Jhanjharpur, Bethauli and Begusarai, along with the associated transformation capacity.
The transmission network will comprise the 400 kV double-circuit (DCDS) Pirpainti–Jhanjharpur, Pirpainti–Begusarai and Begusarai–Bakhtiyarpur lines, besides the 220 kV DCDS Jhanjharpur–Bethauli and Begusarai–Begusarai Town lines.
The scope also includes the Line-In-Line-Out (LILO) arrangement for existing 220 kV and 132 kV transmission lines at Jhanjharpur and the construction of 400 kV line bays at Bakhtiyarpur Grid Substation (GSS).
The project marks another addition to AESL’s transmission infrastructure portfolio, with the new network designed to connect large-scale generation capacity to Bihar’s wider electricity grid